Long questions with answers for this topic
te = (to + 4tm + tp) / 6.
A Gantt chart is a bar chart showing activities versus time.
PERT is a scheduling technique using probabilistic time estimates for uncertain activities.
CPM (Critical Path Method) is a scheduling technique to identify the critical path using known activity durations.
Critical path is the longest-duration path in the network and determines minimum project duration.
Float (slack) is the allowable delay for an activity without delaying project completion.
In forward pass, we calculate ES and EF using EF = ES + duration. In backward pass, we calculate LF and LS using LS = LF − duration. These help find float and critical path.